An important project at AMB consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run. No managerial

Advertisements
Advertisements

प्रश्न

An important project at AMB consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run. No managerial action like assigning more workers, equipment or giving overtime has been able to solve the problem. What managerial action may now be taken by the company to avoid such a situation from arising in future?

पर्याय

  • Revise the schedule

  • Assigning additional workers and equipment to the project

  • Get permission for further overtime work

  • Both (2) and (3)

MCQ
Advertisements

उत्तर

Revise the schedule

Explanation - 

Because no managerial effort has been successful in resolving the problem, the manager must revise the timetable to close the gap created by an improper schedule.