Question
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Advertisements
Solution
∵ In 9 months, a part of stadium can complete by 560 persons.
∴ In 1 month, the work can be complete by 9 × 560 = 5040 persons.
∵ In 5 months, the work can be complete by `5040/5` = 1008 persons
Now, number of extra persons required to complete the work in 5 months = 1008 – 560 = 448
APPEARS IN
RELATED QUESTIONS
A factory required 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
In which of the following table x and y vary inversely:
| x | 9 | 24 | 15 | 3 |
| y | 8 | 3 | 4 | 25 |
If x and y vary inversely as other and x = 5 when y = 15, find x when y = 12 .
Three persons can build a small house in 8 days. To build the same house in 6 days, how many persons are required?
If 40 workers can do a project work in 8 days, then _________ workers can do it in 4 days
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Forty students stay in a hostel. They had food stock for 30 days. If the students are doubled then for how many days the stock will last?
A toy company requires 36 machines to produce car toys in 54 days. How many machines would be required to produce the same number of car toys in 81 days?
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The number of people working and the time to complete a given work.
A packet of sweets was distributed among 10 children and each of them received 4 sweets. If it is distributed among 8 children, how many sweets will each child get?