A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
Advertisements
उत्तर
∵ In 9 months, a part of stadium can complete by 560 persons.
∴ In 1 month, the work can be complete by 9 × 560 = 5040 persons.
∵ In 5 months, the work can be complete by `5040/5` = 1008 persons
Now, number of extra persons required to complete the work in 5 months = 1008 – 560 = 448
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The population of a country and the area of land per person.
A car takes 2 hours to reach a destination by travelling at the speed of 60 km/h. How long will it take when the car travels at the speed of 80 km/h?
It x and y vary inversely, fill in the following blank:
| x | 16 | 32 | 8 | 128 |
| y | 4 | ... | ... | 0.25 |
In a hostel of 50 girls, there are food provisions for 40 days. If 30 more girls join the hostel, how long will these provisions last?
A farmer has enough food for 144 ducks for 28 days. If he sells 32 ducks how long will the food last?
Meena had enough money to send 8 parcels each weighing 500 grams through a courier service. What would be the weight of each parcel, if she has to send 40 parcels for the same money?
When the speed is kept fixed, time and distance vary inversely with each other.
When two quantities are related in such a manner that if one increases and the other decreases, then they always vary inversely.
If x varies inversely as y and y = 60 when x = 1.5. Find x. when y = 4.5.
Sobi types 108 words in 6 minutes. How many words would she type in half an hour?