प्रश्न
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The number of people working and the time to complete a given work.
Advertisements
उत्तर
The number of people working and the time to complete a given work are inversely proportional to each other.
E.g. Let 20 workers can complete a work in 1 day.
Then, 10 workers can complete the same work in 2 days.
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The time taken for a journey and the distance travelled in a uniform speed.
A factory required 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
Two persons could fit new windows in house in 3 days.
One of the persons fell ill before the work started. How long would the job take now?
A car can finish a certain journey in 10 hours at the speed of 48 km/hr. By how much should its speed be increased so that it may take only 8 hours to cover the same distance?
Five workers take 12 days to weed a field. How many days would 6 workers take? How many would 15 take?
It takes 120 minutes to weed a garden with 6 gardeners. If the same work is to be done in 30 minutes, how many more gardeners are needed?
x varies inversely as twice of y. Given that when y = 6, the value of x is 4. Find the value of x when y = 8
If a tree 24 m high casts a shadow of 15 m, then the height of a pole that casts a shadow of 6 m under similar conditions is 9.6 m.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The time taken by a train to cover a fixed distance and the speed of the train.
If x varies inversely as y and x = 20 when y = 600, find y when x = 400.