Question
A, B and C can do a piece of work in 12, 15 and 20 days respectively. How long will they take to do it working together?
Advertisements
Solution
A can do a piece of work in 12 days
B can do the same work in 15 days
C can do the same work in 20 days
∴ A's 1 day's work = `1/12`
B's 1 day's work = `1/15`
C's 1 day's work = `1/20`
∴ (A + B + C)'s together 1 day's work
`= 1/12 + 1/15 + 1/20`
`= (5 + 4 + 3)/60 = 12/60 = 1/5`
∴ they can do the work in 5 days.
APPEARS IN
RELATED QUESTIONS
A and B working together can do a piece of work in 10 days B alone can do the same work in 15 days. How long will A alone take to do the same work?
A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in:
- one day
- 2 days
What part of work will be left, after they have worked together for 2 days?
Mohit can complete a work in 50 days, whereas Anuj can complete the same work in 40 days. Find:
(i) work done by Mohit in 20 days.
(ii) work left after Mohit has worked on it for 20 days.
(iii) time taken by Anuj to complete the remaining work.
A train travels 700 metres in 35 seconds. What is its speed in km/h?
Mr. Amit can walk 8 km in 1 hour 20 minutes. How long will it take him to walk:
(i) 2500 m?
(ii) 6.5 km?
| S.No | Speed | Distance | Time (Hours) |
| i | 35 Km/hour | 280 Km | |
| ii | 40 Km/hour | 360 Km | |
| iii | 45 Km/hour | 315 Km | |
| iv | 50 Km/hour | 300 Km | |
| v | 55 Km/hour | 275 Km |
From where you are, what interesting things do you see to your east?
What is the correct relationship between speed (S), distance (D), and time (T)?
A vehicle covers 240 km in 4 hours. What is its speed?
A runner covers 900 m in 3 min. Speed in m s⁻¹ is: