A, B and C can do a piece of work in 12, 15 and 20 days respectively. How long will they take to do it working together?
Advertisements
उत्तर
A can do a piece of work in 12 days
B can do the same work in 15 days
C can do the same work in 20 days
∴ A's 1 day's work = `1/12`
B's 1 day's work = `1/15`
C's 1 day's work = `1/20`
∴ (A + B + C)'s together 1 day's work
`= 1/12 + 1/15 + 1/20`
`= (5 + 4 + 3)/60 = 12/60 = 1/5`
∴ they can do the work in 5 days.
APPEARS IN
संबंधित प्रश्न
A can do a piece of work in 4 days and B can do the same work in 5 days. Find, how much work can be done by them working together in:
- one day
- 2 days
What part of work will be left, after they have worked together for 2 days?
A is able to complete `1/3` of a certain work in 10 hrs and B is able to complete `2/5` of the same work in 12 hrs. Find:
(i) how much work can A do in 1 hour ?
(ii) how much work can B do in 1 hour ?
(iii) in how much time will the work be completed, if both work together.
A, B and C together finish a work in 4 days. If A alone can finish the same work in 8 days and B in 12 days, find how long will C take to finish the work.
A train covers 51 km in 3 hours. Calculate its speed. How far does the train go in 30 minutes?
I travel a distance of 10 km and come back in `2 1/2` hours. What is my speed?
Jagan went to another town such that he covered 240 km by a car going at 60 kmh-1. Then he covered 80 km by a train, going at 100 kmh-1 and the rest 200 km, he covered by a bus, going at 50 kmh-1. What was his average speed during the whole journey?
| S.No | Speed | Distance | Time (Hours) |
| i | 35 Km/hour | 280 Km | |
| ii | 40 Km/hour | 360 Km | |
| iii | 45 Km/hour | 315 Km | |
| iv | 50 Km/hour | 300 Km | |
| v | 55 Km/hour | 275 Km |
Nazar travelled 360 Km at the speed of 90 Km/hour. Find the time taken for his travel
From where you are, what interesting things do you see to your east?
A runner covers 900 m in 3 min. Speed in m s⁻¹ is: