हिंदी
तमिलनाडु बोर्ड ऑफ सेकेंडरी एज्युकेशनएचएससी वाणिज्य कक्षा ११

Draw the network diagram for the following activities. Activity code A B C D E F G Predecessor activity - - A A B C D, E

Advertisements
Advertisements

प्रश्न

Draw the network diagram for the following activities.

Activity code A B C D E F G
Predecessor activity - - A A B C D, E
आकृति
Advertisements

उत्तर

shaalaa.com
Network Analysis
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 10: Operations Research - Miscellaneous Problems [पृष्ठ २५२]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 11 TN Board
अध्याय 10 Operations Research
Miscellaneous Problems | Q 8 | पृष्ठ २५२

संबंधित प्रश्न

Draw the event oriented network for the following data:

Events 1 2 3 4 5 6 7
Immediate Predecessors - 1 1 2, 3 3 4, 5 5, 6

Draw the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.

Jobs 1 - 2 1 - 3 2 - 4 3 - 4 3 - 5 4 - 5 4 - 6 5 - 6
Duration 6 5 10 3 4 6 2 9

The following table gives the activities of a project and their duration in days

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 3 - 5 4 - 5
Duration 5 8 6 7 5 4 8

Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.


The following table use the activities in a construction projects and relevant information

Activity 1 - 2 1 - 3 2 - 3 2 - 4 3 - 4 4 - 5
Duration
(in days)
22 27 12 14 6 12

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


In constructing the network which one of the following statements is false?


Which of the following is not correct?


In the context of network, which of the following is not correct


Network problems have the advantage in terms of project


A Project has the following time schedule

Activity 1 - 2 2 - 3 2 - 4 3 - 5 4 - 6 5 - 6
Duration
(in days)
6 8 4 9 2 7

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


The following table gives the characteristics of the project

Activity 1 - 2 1 - 3 2 - 3 3 - 4 3 - 5 4 - 6 5 - 6 6 - 7
Duration
(in days)
5 10 3 4 6 6 5 5

Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×