Question
Twenty-five workers were employed to complete a compound wall in 12 days. Five workers left after working for 4 days. The remaining 20 workers completed the work. In how many days the total job was completed?
Options
15 days
16 days
14 days
18 days
MCQ
Advertisements
Solution
14 days
Explanation:
25 worker complete work in 12 days then ATQ
25 × 12 = 25 × 4 + 20 × x
25 (12− 4) = 20 x
`(25xx8)/20="x"`
x = 10
Total work completed in 10 + 4 = 14 days