Five men can complete a piece of work in 24 days. In how many days will 12 men complete the same piece of work?
Options
8 days
6 days
12 days
10 days
MCQ
Advertisements
Solution
10 days
Explanation:
M1D1 = M2D2
⇒ 15 × 20 = M2 × 25
⇒ `"M"_2 = (15 xx 20)/25` = 12