Find the Sequence that Minimizes Total Elapsed Time (In Hours) Required to Complete the Following Jobs on Two Machines M1 and M2 in Order M1-m2. Also Find the Minimum Elapsed Time - Mathematics and Statistics

Advertisements
Advertisements

Question

Find the sequence that minimizes total elapsed time (in hours) required to complete the following jobs on two machines M1 and M2 in order M1-M2. Also, find the minimum elapsed time T and idle time for the two machines. 

Jobs 
Machines  A B C D E
M1 5 1 9 3 10
M2 2 6 7 8 4
Sum
Advertisements

Solution

Optimal sequence : 

B D C E A

Working Table : 

Minimum elapsed time T = 30 hours 

Idle time for machine M1 

= 30 - 28 = 2 hours 

Idle time for machine M

= 1 + 1 + 1 = 3 hours 