Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Solution:
Using the optimal sequence algorithm, the following optimal sequence can be obtained.
| `square` | `square` | IV | V | III | `square` | `square` |
Total elapsed time is obtained as follows
| Job | Machine A | Machine B | ||
| Time In | Time Out | Time In | Time Out | |
| `square` | 0 | 5 | 5 | 12 |
| `square` | 5 | 12 | 12 | 24 |
| IV | 12 | 22 | 24 | 34 |
| V | 22 | 36 | 36 | 52 |
| III | 36 | 55 | 55 | 69 |
| `square` | 55 | 71 | 71 | 85 |
| `square` | 71 | 86 | 86 | 91 |
∴ Total elapsed time T = 91 units
Idle time for machine A = `square` units
Idle time for machine B = `square` units
Fill in the Blanks
Sum
Advertisements
Solution
Using the optimal sequence algorithm, the following optimal sequence can be obtained.
| \[\boxed{VII}\] | \[\boxed{I}\] | IV | V | III | \[\boxed{II}\] | \[\boxed{VI}\] |
Total elapsed time is obtained as follows
| Job | Machine A | Machine B | ||
| Time In | Time Out | Time In | Time Out | |
| \[\boxed{VII}\] | 0 | 5 | 5 | 12 |
| \[\boxed{I}\] | 5 | 12 | 12 | 24 |
| IV | 12 | 22 | 24 | 34 |
| V | 22 | 36 | 36 | 52 |
| III | 36 | 55 | 55 | 69 |
| \[\boxed{II}\] | 55 | 71 | 71 | 85 |
| \[\boxed{VI}\] | 71 | 86 | 86 | 91 |
∴ Total elapsed time T = 91 units
Idle time for machine A = \[\boxed{5}\] units
Idle time for machine B = \[\boxed{13}\] units