मराठी
महाराष्ट्र राज्य शिक्षण मंडळएचएससी वाणिज्य (इंग्रजी माध्यम) इयत्ता १२ वी

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines. - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.

Job I II III IV V VI VII
Machine A 7 16 19 10 14 15 5
Machine B 12 14 14 10 16 5 7

Solution:

Using the optimal sequence algorithm, the following optimal sequence can be obtained.

`square` `square` IV III `square` `square`

Total elapsed time is obtained as follows

Job Machine A Machine B
Time In Time  Out Time In Time Out
`square` 0 5 5 12
`square` 5 12 12 24
IV 12 22 24 34
V 22 36 36 52
III 36 55 55 69
`square` 55 71 71 85
`square` 71 86 86 91

∴ Total elapsed time T = 91 units

Idle time for machine A = `square` units

Idle time for machine B = `square` units

रिकाम्या जागा भरा
बेरीज
Advertisements

उत्तर

Using the optimal sequence algorithm, the following optimal sequence can be obtained.

\[\boxed{VII}\] \[\boxed{I}\] IV III \[\boxed{II}\] \[\boxed{VI}\]

Total elapsed time is obtained as follows

Job Machine A Machine B
Time In Time  Out Time In Time Out
\[\boxed{VII}\] 0 5 5 12
\[\boxed{I}\] 5 12 12 24
IV 12 22 24 34
V 22 36 36 52
III 36 55 55 69
\[\boxed{II}\] 55 71 71 85
\[\boxed{VI}\] 71 86 86 91

∴ Total elapsed time T = 91 units

Idle time for machine A = \[\boxed{5}\] units

Idle time for machine B = \[\boxed{13}\] units