प्रश्न
Find the sequence that minimizes the total elapsed time to complete the following jobs in the order AB. Find the total elapsed time and idle times for both the machines.
| Job | I | II | III | IV | V | VI | VII |
| Machine A | 7 | 16 | 19 | 10 | 14 | 15 | 5 |
| Machine B | 12 | 14 | 14 | 10 | 16 | 5 | 7 |
Solution:
Using the optimal sequence algorithm, the following optimal sequence can be obtained.
| `square` | `square` | IV | V | III | `square` | `square` |
Total elapsed time is obtained as follows
| Job | Machine A | Machine B | ||
| Time In | Time Out | Time In | Time Out | |
| `square` | 0 | 5 | 5 | 12 |
| `square` | 5 | 12 | 12 | 24 |
| IV | 12 | 22 | 24 | 34 |
| V | 22 | 36 | 36 | 52 |
| III | 36 | 55 | 55 | 69 |
| `square` | 55 | 71 | 71 | 85 |
| `square` | 71 | 86 | 86 | 91 |
∴ Total elapsed time T = 91 units
Idle time for machine A = `square` units
Idle time for machine B = `square` units
रिकाम्या जागा भरा
बेरीज
Advertisements
उत्तर
Using the optimal sequence algorithm, the following optimal sequence can be obtained.
| \[\boxed{VII}\] | \[\boxed{I}\] | IV | V | III | \[\boxed{II}\] | \[\boxed{VI}\] |
Total elapsed time is obtained as follows
| Job | Machine A | Machine B | ||
| Time In | Time Out | Time In | Time Out | |
| \[\boxed{VII}\] | 0 | 5 | 5 | 12 |
| \[\boxed{I}\] | 5 | 12 | 12 | 24 |
| IV | 12 | 22 | 24 | 34 |
| V | 22 | 36 | 36 | 52 |
| III | 36 | 55 | 55 | 69 |
| \[\boxed{II}\] | 55 | 71 | 71 | 85 |
| \[\boxed{VI}\] | 71 | 86 | 86 | 91 |
∴ Total elapsed time T = 91 units
Idle time for machine A = \[\boxed{5}\] units
Idle time for machine B = \[\boxed{13}\] units