English

Find the sequence of the following five jobs to be processed on three machines M1 M2,, M3 that will minimize the total elapsed time to complete the tasks. - Mathematics and Statistics

Advertisements
Advertisements

Question

Find the sequence of the following five jobs to be processed on three machines M1 M2,, M3 that will minimize the total elapsed time to complete the tasks. Each job is to be processed in the order M1 - M2 - M3:

Jobs 1 2 3 4 5
Machine M1 5 11 5 7 6
Machine M2 1 4 2 5 3
Machine M3  1 5 2 3 4
Sum
Advertisements

Solution

Min(M1) = 5, Max(M2) = 5, Min(M3) =  1

Min (M1) ≥ Max (M2

∴ Min(M3) ≥ Max (M2) is satisfied.

G = M1 + M3 and H = M2 + M3

Jobs 1 2 3 4 5
MG 6 15 7 12 9
MH 2 9 4 8 7

∴ The required sequence is 

2 4 5 3 1

The table of total elapsed time is as follows: 

Job Machine (M1) Machine (M2) Machine (M3)
In Out In Out In Out
2 0 11 11 15 15 20
4 11 18 18 23 23 26
5 18 24 24 27 27 31
3 24 29 29 31 31 33
1 29 34 34 35 35 36

Total elapsed time = 36 units. 

Idle time for M1 = 2 units

Idle time for M2 = 21 units

Idle time for M3 = 21 units

shaalaa.com
Sequencing in Management Mathematics
  Is there an error in this question or solution?
2017-2018 (July) Set 1

APPEARS IN

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×