Amar Builders undertook a contract for Rs. 10,00,000. The following expenses were incurred for this contract during the year 2016 -17:
| Particulars | (Rs.) |
| Material sent to site | 3,10,000 |
| Direct wages paid | 2,80,000 |
| Chargeable Expenses | 60,000 |
| Plant Installed | 1,00,000 |
| General Expenses | 90,000 |
| Establishment Charges | 70,000 |
The architect of contractee certified work of 6,00,000 at the end of year. The cost of work uncertified was Rs. 50,000 on that date. The material and plant were at site of 30,000 and Rs. 60,000 respectively at the end of the year.
You are required to prepare Contract Account and show how these transactions will appear in the Balance Sheet of the contractor at the end ofthe year.
Advertisements
Solution
Books of Amar Builder
| Dr. | Contract Alc | Cr. |
| Particulars | (Rs.) | Particulars | (Rs.) |
| To Material -Sent to Site | 3,10,000 | By Work Certified | 6,00,000 |
| To Direct Wages Paid | 2,80,000 | By Work Uncertified | 50,000 |
| To Chargeable Expenses | 60,000 | By Material at Site | 30,000 |
| To Plant Installed | 1,00,000 | By Plant at Site | 60,000 |
| To General Expenses | 90,000 | By Notional Loss c/d | 1,70,000 |
| To Establishment Charges | 70,000 | ||
| 9,10,000 | 9,10,000 |
Extracts of Balance Sheet (For the Year Ended 31-12-2017)
| Liabilities | (Rs.) | Assets | (Rs.) | |
| Material at Site | 30,000 | |||
| Plant at Site | 60,000 | |||
| Work-in-Progress: | ||||
| Work Certified | 6,00,000 | |||
| (+) Work Uncertified | 50,000 | |||
| 6,50,000 | ||||
| (-) Cash Received | - | |||
| 6,50,000 | ||||
| (-) Stock Reserve | - | 6,50,000 |