Amar Builders Undertook a Contract for Rs. 10,00,000. the Following Expenses Were Incurred for this Contract During the Year 2016 -17:

Advertisements
Advertisements

प्रश्न

Amar Builders undertook a contract for Rs. 10,00,000. The following expenses were incurred for this contract during the year 2016 -17: 

Particulars (Rs.)
Material sent to site 3,10,000
Direct wages paid 2,80,000
Chargeable Expenses 60,000
Plant Installed 1,00,000
General Expenses 90,000
Establishment Charges 70,000

The architect of contractee certified work of 6,00,000 at the end of year. The cost of work uncertified was Rs. 50,000 on that date. The material and plant were at site of 30,000 and Rs. 60,000 respectively at the end of the year.
You are required to prepare Contract Account and show how these transactions will appear in the Balance Sheet of the contractor at the end ofthe year.

Advertisements

उत्तर

Books of Amar Builder

Dr. Contract Alc Cr.
Particulars (Rs.) Particulars (Rs.)
To Material -Sent to Site 3,10,000 By Work Certified 6,00,000
To Direct Wages Paid 2,80,000 By Work Uncertified 50,000
To Chargeable Expenses 60,000 By Material at Site 30,000
To Plant Installed 1,00,000 By Plant at Site 60,000
To General Expenses 90,000 By Notional Loss c/d 1,70,000
To Establishment Charges 70,000    
  9,10,000   9,10,000

Extracts of Balance Sheet (For the Year Ended 31-12-2017)

Liabilities (Rs.) Assets   (Rs.)
    Material at Site   30,000
    Plant at Site   60,000
    Work-in-Progress:    
    Work Certified 6,00,000  
    (+) Work Uncertified 50,000  
      6,50,000  
    (-) Cash Received -  
      6,50,000  
    (-) Stock Reserve - 6,50,000