Question
A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?
Advertisements
Solution
Let the number of days required by 4 persons to complete the job be x.
The following table is obtained.
| Number of days | 4 | x |
| Number of persons | 3 | 4 |
If the number of persons is more, then it will take less time to complete the job.
Hence, the number of days and the number of persons required to complete the job are inversely proportional to each other.
Therefore,
4 × 3 = x × 4
`x = (4 xx3)/4`
x = 3
Therefore, 4 persons will take 3 days to complete the job.
APPEARS IN
RELATED QUESTIONS
It x and y vary inversely, fill in the following blank:
| x | 16 | 32 | 8 | 128 |
| y | 4 | ... | ... | 0.25 |
55 cows can graze a field in 16 days. How many cows will graze the same field in 10 days?
Three persons can build a small house in 8 days. To build the same house in 6 days, how many persons are required?
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
It takes 120 minutes to weed a garden with 6 gardeners. If the same work is to be done in 30 minutes, how many more gardeners are needed?
When two quantities x and y are in ______ proportion or vary ______ they are written as `x oo 1/y`.
Both x and y are said to vary ______ with each other if for some positive number k, xy = k.
If x varies inversely as y, then
| x | – | 60 |
| y | 2 | 10 |
If a and b vary inversely to other, then find the values of p, q, r ; x, y, z and l, m, n.
| a | 2 | y | 6 | 10 |
| b | x | 12.5 | 15 | z |