Question
A computers centre has four expert programmers . The centre needs four application programmes to be developed. The head of the computer centre , after stying carefully the programmes to be developed , estimates the computer time in minutes required by the respective experts to develop the application programmes as follows :
| Programmes | ||||
| Programmes | 1 | 2 | 3 | 4 |
| (Times in minutes) | ||||
| A | 120 | 100 | 80 | 90 |
| B | 80 | 90 | 110 | 70 |
| C | 110 | 140 | 120 | 100 |
| D | 90 | 90 | 80 | 90 |
How should the head of the computer centre assign the programmes to the programmers so that the total time required is minimum ?
Sum
Advertisements
Solution
After subtracting minimum value from each row:

After subtracting minimum value from each column.

Minimum number of lines covering al zeroes
Allot the single zero· first in rows and then in column.

∴ Assignment
A → 3, B → 1, C→ 4. D → 2
Total minimum time
80 + 80 + 100 + 90 = 350