प्रश्न
Two persons could fit new windows in house in 3 days.
One of the persons fell ill before the work started. How long would the job take now?
Advertisements
उत्तर
Let the number of days required by 1 man to fit all the windows be x. The following table is obtained.
| Number of persons | 2 | 1 |
| Number of days | 3 | x |
Lesser the number of persons, more will be the number of days required to fit all the windows. Hence, this is a case of inverse proportion.
Therefore,
2 × 3 = 1 × x
x = 6
Hence, the number of days taken by 1 man to fit all the windows is 6.
APPEARS IN
संबंधित प्रश्न
Which of the following are in inverse proportion?
The time taken for a journey and the distance travelled in a uniform speed.
Which of the following are in inverse proportion?
The time taken for a fixed journey and the speed of the vehicle.
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
55 cows can graze a field in 16 days. How many cows will graze the same field in 10 days?
The stock of grain in a government warehouse lasts 30 days for 4000 people. How many days will it last for 6000 people?
A flood relief camp has food stock by which 80 people can be benefited for 60 days. After 10 days 20 more people have joined the camp. Calculate the number of days of food shortage due to the addition of 20 more people?
A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
If a and b vary inversely to other, then find the values of p, q, r ; x, y, z and l, m, n.
| a | 2 | y | 6 | 10 |
| b | x | 12.5 | 15 | z |
Two persons could fit new windows in house in 3 days.
How many persons would be needed to fit the windows in one day?