मराठी

Two persons could fit new windows in house in 3 days. One of the persons fell ill before the work started. How long would the job take now?

Advertisements
Advertisements

प्रश्न

Two persons could fit new windows in house in 3 days.

One of the persons fell ill before the work started. How long would the job take now?

बेरीज
Advertisements

उत्तर

Let the number of days required by 1 man to fit all the windows be x. The following table is obtained.

Number of persons 2 1
Number of days 3 x

Lesser the number of persons, more will be the number of days required to fit all the windows. Hence, this is a case of inverse proportion.

Therefore,

2 × 3 = 1 × x

x = 6

Hence, the number of days taken by 1 man to fit all the windows is 6.

shaalaa.com
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
पाठ 11: Direct and Inverse Proportions - EXERCISE 11.2 [पृष्ठ १४२]

APPEARS IN

एनसीईआरटी Mathematics [English] Class 8
पाठ 11 Direct and Inverse Proportions
EXERCISE 11.2 | Q 10. (i) | पृष्ठ १४२

व्हिडिओ ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्‍न

Which of the following are in inverse proportion?

The number of workers on a job and the time to complete the job.


A farmer has enough food to feed 20 animals in his cattle for 6 days. How long would the food last if there were 10 more animals in his cattle?


A batch of bottles was packed in 25 boxes with 12 bottles in each box. If the same batch is packed using 20 bottles in each box, how many boxes would be filled?


The stock of grain in a government warehouse lasts 30 days for 4000 people. How many days will it last for 6000 people?


Meena had enough money to send 8 parcels each weighing 500 grams through a courier service. What would be the weight of each parcel, if she has to send 40 parcels for the same money?


In a school there is 7 periods a day each of 45 minutes duration. How long each period is if the school has 9 periods a day assuming the number of hours to be the same?


Six men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?


A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?


If a and b vary inversely to other, then find the values of p, q, r ; x, y, z and l, m, n.

a 2 y 6 10
b x 12.5 15 z

The variable x is inversely proportional to y. If x increases by p%, then by what per cent will y decrease?


Share