प्रश्न
The time taken to assemble a car in a certain plant is a random variable having a normal distribution of 20 hours and a standard deviation of 2 hours. What is the probability that a car can be assembled at this plant in a period of time. Less than 19.5 hours?
Advertisements
उत्तर
Let x denotes the time taken to assemable cars mean µ = 20 hours and S.D σ = 2 hours
The standard normal variate
z = `(x - mu)/sigma`
= `(x - 20)/2`
P(less than 19.5 hours) = P(X < 19.5)
When x = 19.5
z = `19.5/2`
= `(-0.5)/2`
= 0.25
P(X < 19.5) = P(Z < – 0.25)
= P(`-oo` < z < 0) – P(– 0.25 < z < 0)
= 0.5 – P(0 < z < 0.25)
= 0.5 – 0.0987
= 0.4013
APPEARS IN
संबंधित प्रश्न
Define Bernoulli trials
If 18% of the bolts produced by a machine are defective, determine the probability that out of the 4 bolts chosen at random none will be defective
If 18% of the bolts produced by a machine are defective, determine the probability that out of the 4 bolts chosen at random atmost 2 will be defective
Among 28 professors of a certain department, 18 drive foreign cars and 10 drive local made cars. If 5 of these professors are selected at random, what is the probability that atleast 3 of them drive foreign cars?
Consider five mice from the same litter, all suffering from Vitamin A deficiency. They are fed a certain dose of carrots. The positive reaction means recovery from the disease. Assume that the probability of recovery is 0.73. What is the probability that atleast 3 of the 5 mice recover
The average number of customers, who appear in a counter of a certain bank per minute is two. Find the probability that during a given minute no customer appears
In a test on 2,000 electric bulbs, it was found that bulbs of a particular make, was normally distributed with an average life of 2,040 hours and standard deviation of 60 hours. Estimate the number of bulbs likely to burn for more 1,920 hours but less than 2,100 hours
Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct the flyover in 450 days or less and agree to pay a penalty of ₹ 10,000 for each labour day spent in excess of 450. What is the probability that the company takes at most 500 days to complete the flyover?
Choose the correct alternative:
If P(Z > z) = 0.5832 what is the value of z (z has a standard normal distribution)?
X is a normally distributed variable with mean µ = 30 and standard deviation σ = 4. Find P(X < 40)