Question
Two men A and B, each working alone by working 12 hours per day, can complete a work in 20 days. For execution of the work, it was decided that A and B would be working for 8 and 6 hours per day, respectively, on alternate days starting with A. If it takes x days and y hours to complete the work then (x, y) is:
Options
(34, 4)
(33, 4)
(33, 2)
(34, 2)
MCQ
Solution
(34, 2)
Explanation:
A complete work in 20 days
A works 12 hours per day.
∴ Total work = 20 × 12 = 240
Now, A works for 8 hours a day.
B work for 6 hours a day.
So, work done in 2 days = 8 + 6 = 14
∴ No. of days = `240/14 = 17 2/14` = 17 × 2 = 34 days
And `1/7` work remain
So, `1/7 xx 14` = 2 hours
∴ x = 34 and y = 2