Question

From the following details, Calculate :
(i) Labour Cost Variance,
(ii) Labour Rate Variance,
(iii) Labour Efficiency Variance,
(iv) Labour Mix Variance.

Workers Standard Actual
Hours Rate(Rs.) Total(Rs.) Hours Rate(Rs.) Total(Rs.)
Skilled 30 5.00 150 32 5 160
Unskilled 40 4.00 160 32 4.25 136
  70   310 64   296

 

Advertisements

Solution

Workers Standard Actual Std. Proportion of Actual Input (Hours)

Hours Rate(Rs.) Total(Rs.) Hours Rate(Rs.) Total(Rs.)
Skilled 30 5.00 150 32 5 160 27
Unskilled 40 4.00 160 32 4.25 136 37
  70   310 64   296 64

(i) Labour Cost Variance (LCV) = (Std. Hrs. x SR) - (Actual Hrs x AR)
∴ Skilled = (30 x 5) - (32 x 5)"
= Rs. 150 (-) Rs. 160
∴ Skilled = Rs. 10 (A)
Unskilled = ( 40 x 4) - (32 x 4.25)
= Rs. 160 - Rs. 136
∴ Unskilled = Rs. 24 (F)
∴ LCV = Rs. 14 (F)

(ii) Labour Rate Variance (LRV) = (SR - AR) x Actual Hrs.
Skilled = (5 - 5) x 32 = Rs.Nil
Unskilled = (4 - 4.25) x 32 = Rs. 8 (A)
Rs. 8 (A)

(iii) Labour Efficiency Variance (LEV) = (Std. Hrs. - Actual Hrs.) x SR
Skilled = (30 - 32) x 5 = Rs. 10 (A)
Unskilled = ( 40 - 32) x 4 = Rs. 32 (F)
Rs. 22 (F)

(iv) Labour Mix Variance (LMV) = SR x Difference in Mix
Skilled = 5 x (27- 32) = Rs. 25 (A)
Unskilled = 4 x (37- 32) = Rs. 20 (F)
Rs. 5 (A)