Advertisements
Advertisements
Question
2 men and 7 boys complete a certain piece of work in 8 days. 4 men and 4 boys can do the same in only 6 days. Find the number of days required to complete the work by 1 man.
Advertisements
Solution
Let the work done by 1 man in one day be x, and by 1 boy be y,
According to the given conditions,
First condition:
(2x + 7y) × 8 = 1
16x + 56y = 1 ...(1)
Second condition:
(4x + 4y) × 6 = 1
24x + 24y = 1 ...(2)
Now, solving the two equations,
Multiplying equation (1) by 3:
3(16x + 56y) = 3(1)
48x + 168y = 3 ...(3)
Multiplying equation (2) by 7:
7(24x + 24y) = 7(1)
168x + 168y = 7 ...(4)
Subtracting equation (3) from equation (4):
(168x + 168y) − (48x + 168y) = 7 − 3
168x + 168y − 48x − 168y = 4
168x − 48x = 4
120x = 4
x = `4/120`
∴ x = `1/30`
So, 1 man does `1/30` of the work in one day.
Hence, 1 man can complete the work in 30 days.
