मराठी
महाराष्ट्र राज्य शिक्षण मंडळएचएससी वाणिज्य (इंग्रजी माध्यम) इयत्ता १२ वी

In a Factory There Are Six Jobs to Be Performed Each of Which Should Go Through Two Machines a and B in the Order a - B - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

In a factory there are six jobs to be performed each of which should go through two machines A and B in the order A - B. The processing timing (in hours) for the jobs arc given here. You are required to determine the sequence for performing the jobs that would minimize the total elapsed time T. What is the value of T? Also find the idle time for machines · A and B.

Jobs J1 J2 J3 J4 J5 J6
Machine A 1 3 8 5 6 3
MAchine B 5 6 3 2 2 10
बेरीज
Advertisements

उत्तर

The order is A to B, hence the required sequence is

J1 J2 J6 J3 J5 J4

or

J1 J6 J2 J3 J4 J5

 

Job
Sequence
Machine A Machine B
Time
in
Time
out
Time
in
Time
out
J1 0 1 1 6
J2 1 4 6 12
J6 4 7 12 22
J3 7 15 22 25
J5 15 21 25 27
J4 21 26 27 29

Total elapsed time T = 29 hours
Idle time for A = 3 hours
Idle time for B = 1 hour.

shaalaa.com
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
2013-2014 (October)

APPEARS IN

व्हिडिओ ट्यूटोरियलVIEW ALL [1]

संबंधित प्रश्‍न

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job is given in the following table:

         Jobs

 

 

                          Machines

P

Q

R

S

                Processing Cost (Rs.)

 

A

31

25

33

29

B

25

24

23

21

C

19

21

23

24

D

38

36

34

40

 How should the jobs be assigned to the four machines so that the total processing cost is minimum?


Solve the following minimal assignment problem and hence find the minimum value : 

  I II III IV
A 2 10 9 7
B 13 2 12 2
C 3 4 6 1
D 4 15 4 9

 


Suggest optimum solution to the following assignment. Problem, also find the total minimum service time.
                                             Service Time ( in hrs.)

Counters Salesmen
A B C D
W 41 72 39 52
X 22 29 49 65
Y 27 39 60 51
Z 45 50 48 52

Determine `l_92 and l_93, "given that"  l_91 = 97, d_91 = 38 and q_92 = 27/59`


Solve the following minimal assignment problem and hence find minimum time where  '- ' indicates that job cannot be assigned to the machine : 

Machines Processing time in hours
A B C D E
M1 9 11 15 10 11
M2 12 9 - 10 9
M3 - 11 14 11 7
M4 14 8 12 7 8

A job production unit has four jobs A, B, C, D which can be manufactured on each of the four machines P, Q, R and S. The processing cost of each job for each machine is given in the following table:

Jobs Machines
(Processing Cost in ₹)
P Q R S
A 31 25 33 29
B 25 24 23 21
C 19 21 23 24
D 38 36 34 40

Find the optimal assignment to minimize the total processing cost.


Five different machines can do any of the five required jobs, with different profits resulting from each assignment as shown below:

Job Machines (Profit in ₹)
A B C D E
1 30 37 40 28 40
2 40 24 27 21 36
3 40 32 33 30 35
4 25 38 40 36 36
5 29 62 41 34 39

Find the optimal assignment schedule.


The assignment problem is said to be balanced if ______.


Choose the correct alternative :

The assignment problem is said to be balanced if it is a ______.


Choose the correct alternative :

In an assignment problem if number of rows is greater than number of columns then


Solve the following problem :

A plant manager has four subordinates, and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. This estimate of the time each man would take to perform each task is given in the effectiveness matrix below.

  I II III IV
A 7 25 26 10
B 12 27 3 25
C 37 18 17 14
D 18 25 23 9

How should the tasks be allocated, one to a man, as to minimize the total man hours?


In an assignment problem if number of rows is greater than number of columns, then dummy ______ is added


State whether the following statement is True or False: 

In assignment problem each worker or machine is assigned only one job


What is the difference between Assignment Problem and Transportation Problem?


Three jobs A, B and C one to be assigned to three machines U, V and W. The processing cost for each job machine combination is shown in the matrix given below. Determine the allocation that minimizes the overall processing cost.

    Machine
    U V W
Jobs A 17 25 31
B 10 25 16
C 12 14 11

(cost is in ₹ per unit)


A departmental head has four subordinates and four tasks to be performed. The subordinates differ in efficiency and the tasks differ in their intrinsic difficulty. His estimates of the time each man would take to perform each task is given below:

    Tasks
    1 2 3 4
Subordinates P 8 26 17 11
  Q 13 28 4 26
  R 38 19 18 15
  S 9 26 24 10

How should the tasks be allocated to subordinates so as to minimize the total manhours?


Assign four trucks 1, 2, 3 and 4 to vacant spaces A, B, C, D, E and F so that distance travelled is minimized. The matrix below shows the distance.

  1 2 3 4
A 4 7 3 7
B 8 2 5 5
C 4 9 6 9
D 7 5 4 8
E 6 3 5 4
F 6 8 7 3

A natural truck-rental service has a surplus of one truck in each of the cities 1, 2, 3, 4, 5 and 6 and a deficit of one truck in each of the cities 7, 8, 9, 10, 11 and 12. The distance(in kilometers) between the cities with a surplus and the cities with a deficit are displayed below:

    To
    7 8 9 10 11 12
From 1 31 62 29 42 15 41
2 12 19 39 55 71 40
3 17 29 50 41 22 22
4 35 40 38 42 27 33
5 19 30 29 16 20 33
6 72 30 30 50 41 20

How should the truck be dispersed so as to minimize the total distance travelled?


A department store has four workers to pack goods. The times (in minutes) required for each worker to complete the packings per item sold is given below. How should the manager of the store assign the jobs to the workers, so as to minimize the total time of packing?

Workers Packing of
  Books Toys Crockery Cutlery
A 3 11 10 8
B 13 2 12 12
C 3 4 6 1
D 4 15 4 9

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×