प्रश्न
Five workers take 12 days to weed a field. How many days would 6 workers take? How many would 15 take?
Advertisements
उत्तर
Let us suppose 6 workers will take x days to weed a field.
As the number of workers increases, the number of days decreases.
So, the number of workers and number of days are in inverse proportion.
∴ 5 × 12 = 6 × x
⇒ x = `60/6`
⇒ x = 10 days
Let us suppose 15 workers will take y days to weed a field.
∴ 5 × 12 = 15 × y
⇒ y = `60/15`
⇒ y = 4 days
Hence, 6 workers will take 10 days, while 15 workers will take 4 days to weed a field.
संबंधित प्रश्न
A car takes 2 hours to reach a destination by travelling at the speed of 60 km/h. How long will it take when the car travels at the speed of 80 km/h?
1200 soldiers in a fort had enough food for 28 days. After 4 days, some soldiers were transferred to another fort and thus the food lasted now for 32 more days. How many soldiers left the fort?
Three spraying machines working together can finish painting a house in 60 minutes. How long will it take for 5 machines of the same capacity to do the same job?
18 men can reap a field in 35 days. For reaping the same field in 15 days, how many men are required?
6 pipes are required to fill a tank in 1 hour 20 minutes. How long will it take if only 5 pipes of the same type are used?
If 40 workers can do a project work in 8 days, then _________ workers can do it in 4 days
Which of the following vary inversely with each other?
Both x and y are said to vary ______ with each other if for some positive number k, xy = k.
If x and y are in inverse proportion, then (x + 1) and (y + 1) are also in inverse proportion.
If a and b vary inversely to other, then find the values of p, q, r ; x, y, z and l, m, n.
| a | 2 | y | 6 | 10 |
| b | x | 12.5 | 15 | z |