प्रश्न
Consider the following transportation problem.
| D1 | D2 | D3 | D4 | Availability | |
| O1 | 5 | 8 | 3 | 6 | 30 |
| O2 | 4 | 5 | 7 | 4 | 50 |
| O3 | 6 | 2 | 4 | 6 | 20 |
| Requirement | 30 | 40 | 20 | 10 |
Determine initial basic feasible solution by VAM.
Advertisements
उत्तर
Let ‘ai‘ denote the availability and ’bj‘ denote the requirement
`sum"a"_"i"` = 30 + 50 + 20 = 100 and `sum"b"_"j"` = 30 + 40 + 20 + 10 = 100
`sum"a"_"i" = sum"b"_"j"`
So the given problem is a balanced transportation problem.
Hence there exists a feasible solution to the given problem.
For VAM, we first find the penalties for rows and columns.
We allocate units to the maximum penalty column (or) row with the least cost.
First allocation:
| D1 | D2 | D3 | D4 | (ai) | Penalty | |
| O1 | 5 | 8 | 3 | 6 | 30 | (2) |
| O2 | 4 | 5 | 7 | 4 | 50 | (1) |
| O3 | 6 | (20)2 | 4 | 6 | 20/0 | (2) |
| (bj) | 30 | 40/20 | 20 | 10 | ||
| Penalty | (1) | (3) | (1) | (2) |
Largest penalty = 3. allocate min (40, 20) to (O3, D2)
Second allocation:
| D1 | D2 | D3 | D4 | (ai) | Penalty | |
| O1 | 5 | 8 | (20)3 | 6 | 30/10 | (2) |
| O2 | 4 | 5 | 7 | 4 | 50 | (1) |
| (bj) | 30 | 20 | 20/0 | 10 | ||
| Penalty | (1) | (3) | (4) | (2) |
Largest penalty = 4.
Allocate min (20, 30) to (O1, D3)
Third allocation:
| D1 | D2 | D4 | (ai) | Penalty | |
| O1 | 5 | 8 | 6 | 10 | (1) |
| O2 | 4 | (20)5 | 4 | 50/30 | (1) |
| (bj) | 30 | 20/0 | 10 | ||
| Penalty | (1) | (3) | (2) |
The largest penalty is 3.
Allocate min (20, 50) to (O2, D2)
Fourth allocation:
| D1 | D4 | (ai) | Penalty | |
| O1 | 5 | 6 | 10 | (1) |
| O2 | 4 | (10)4 | 30/20 | (0) |
| (bj) | 30 | 10/10 | ||
| Penalty | (1) | (2) |
The largest penalty is 2.
Allocate min (10, 30) to (O2, D4)
Fifth allocation:
| D1 | (ai) | Penalty | |
| O1 | (10)5 | 10/0 | – |
| O2 | (20)4 | 20/0 | – |
| (bj) | 30/10/0 | ||
| Penalty | (1) |
The largest penalty is 1.
Allocate min (30, 20) to (O2, D1)
Balance 10 units we allot to (O1, D1).
Thus we have the following allocations:
| D1 | D2 | D3 | D4 | (ai) | |
| O1 | (10)5 | 8 | (20)3 | 6 | 30 |
| O2 | (20)4 | (20)5 | 7 | (10)4 | 50 |
| O3 | 6 | (20)2 | 4 | 6 | 20 |
| (bj) | 30 | 40 | 20 | 10 |
Transportation schedule:
O1 → D1
O1 → D3
O2 → D1
O2 → D2
O2 → D4
O3 → P2
i.e x11 = 10
x13 = 20
x21 = 20
x22 = 20
x24 = 10
x32 = 20
Total cost = (10 × 5) + (20 × 3) + (20 × 4) + (20 × 5) + (10 × 4) + (20 × 2)
= 50 + 60 + 80 + 100 + 40 + 40
= 370
Thus the least cost by YAM is ₹ 370.
APPEARS IN
संबंधित प्रश्न
What is transportation problem?
What is feasible solution and non degenerate solution in transportation problem?
Find the initial basic feasible solution of the following transportation problem:
| I | II | III | Demand | |
| A | 1 | 2 | 6 | 7 |
| B | 0 | 4 | 2 | 12 |
| C | 3 | 1 | 5 | 11 |
| Supply | 10 | 10 | 10 |
Using North West Corner rule
Find the initial basic feasible solution of the following transportation problem:
| I | II | III | Demand | |
| A | 1 | 2 | 6 | 7 |
| B | 0 | 4 | 2 | 12 |
| C | 3 | 1 | 5 | 11 |
| Supply | 10 | 10 | 10 |
Using Vogel’s approximation method
Choose the correct alternative:
In a non – degenerate solution number of allocation is
Choose the correct alternative:
In a degenerate solution number of allocations is
Choose the correct alternative:
The Penalty in VAM represents difference between the first ______
Choose the correct alternative:
In an assignment problem the value of decision variable xij is ______
The following table summarizes the supply, demand and cost information for four factors S1, S2, S3, S4 Shipping goods to three warehouses D1, D2, D3.
| D1 | D2 | D3 | Supply | |
| S1 | 2 | 7 | 14 | 5 |
| S2 | 3 | 3 | 1 | 8 |
| S3 | 5 | 4 | 7 | 7 |
| S4 | 1 | 6 | 2 | 14 |
| Demand | 7 | 9 | 18 |
Find an initial solution by using north west corner rule. What is the total cost for this solution?
Consider the following transportation problem
| Detination | Availabiity | ||||
| D1 | D2 | D3 | D4 | ||
| O1 | 5 | 8 | 3 | 6 | 30 |
| O2 | 4 | 5 | 7 | 4 | 50 |
| O3 | 6 | 2 | 4 | 6 | 20 |
| Requirement | 30 | 40 | 20 | 10 | |
Determine an initial basic feasible solution using Least cost method