A block of mass 30 kg is pulled up by a rope as shown in Fig. with a constant speed by applying a force of 200 N parallel to the slope.

Advertisements
Advertisements

प्रश्न

A block of mass 30 kg is pulled up by a rope as shown in Fig. with a constant speed by applying a force of 200 N parallel to the slope. P and Q are the initial and the final positions of the block respectively. Calculate:

  1. the work done by the force in moving the block from P to Q.
  2. the potential energy gained by the block.
  3. account for the difference in work done by the force and the increase in potential energy of the block.

संख्यात्मक
Advertisements

उत्तर

Given: Mass of block, m = 30 kg

Applied force, F = 200 N

Distance along the slope, s = 3 m

Vertical height gained, h = 1.5 m

Taking, g = 10 m s−2

(a) Work done by the force 

W = F × s

= 200 × 3

= 600 J

(b) Potential energy gained by the block

PE = mgh

PE = 30 × 10 × 1.5

= 450 J

(c) Difference between work done and increase in potential energy 

W − ΔPE

600 − 450 = 150 J

This difference is the work done against friction between the block and the inclined surface. It is mainly converted into heat energy.

shaalaa.com
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 1: Force, Work, Energy and Power - 1.5 Graded Assignment [पृष्ठ ५७]

APPEARS IN

फ्रैंक Physics Part 2 [English] Class 10 ICSE
अध्याय 1 Force, Work, Energy and Power
1.5 Graded Assignment | Q 64. | पृष्ठ ५७
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×