A machine raises a load of 750 N through a height of 16 m in 5 s. calculate:
- energy spent by machine,
- power at which the machine works.
Advertisements
उत्तर
- Energy spent by machine or work done = F × S
Work, W = 750 × 16 = 12000J - Power spent = `"work done"/"time taken " = "12000j"/"5s" = 2400 "w"`
APPEARS IN
संबंधित प्रश्न
Work is said to be done by a forte only when ................
How much work is done when a force of 2 N moves a body through a distance of 10 cm in the direction of force?
The work done on an object does not depend on the :
Give two examples of work done.
Complete the following sentences:
Kilowatt is the unit of ....... and kWh is the unit of
Fill in the boxe to show the corresponding energy transformation.

State the amount of work done by an object when it moves in a circular path for one complete rotation. Give a reason to justify your answer.
State larger units of power.
A force is applied on a body of mass 20 kg moving with a velocity of 40 ms−1. The body attains a velocity of 50 ms−1 in 2 seconds. Calculate the work done by the body.