Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct

Advertisements
Advertisements

प्रश्न

Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct the flyover in 450 days or less and agree to pay a penalty of ₹ 10,000 for each labour day spent in excess of 450. What is the probability that the company pay a penalty of at least ₹ 2,00,000?

योग
Advertisements

उत्तर

Let x be a normal variate with mean 400 labour days and standard deviation of 100 labour days

m = 400 and σ = 100

The construction work should be completed within 450 days.

The standard normal variate

= `(x - mu)/6 = (x - 400)/100`

Personality for 1 labour day = ₹ 10,000

If personality amount is = 2,00,000 than No of excess

Days = `200000/10000` = 20

∴ x = 450 + 20 = 470

When x = 470

z = `(470 - 400)/100 = 70/100` = 0.7

= P(X ≥ 470) = P(Z ≥ 0.7)

= 0.5 – 0.2580

= 0.2420

shaalaa.com
Distribution
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 7: Probability Distributions - Exercise 7.3 [पृष्ठ १६८]

APPEARS IN

सामाचीर कलवी Business Mathematics and Statistics [English] Class 12 TN Board
अध्याय 7 Probability Distributions
Exercise 7.3 | Q 10. (i) | पृष्ठ १६८

संबंधित प्रश्न

Forty percent of business travellers carry a laptop. In a sample of 15 business travelers, what is the probability that 3 will have a laptop?


If the heights of 500 students are normally distributed with mean 68.0 inches and standard deviation 3.0 inches, how many students have height less than or equal to 64 inches


If the heights of 500 students are normally distributed with mean 68.0 inches and standard deviation 3.0 inches, how many students have height between 65 and 71 inches


Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct the flyover in 450 days or less and agree to pay a penalty of ₹ 10,000 for each labour day spent in excess of 450. What is the probability that the company takes at most 500 days to complete the flyover?


Choose the correct alternative:

A manufacturer produces switches and experiences that 2 percent switches are defective. The probability that in a box of 50 switches, there are atmost two defective is :


Choose the correct alternative:

The random variable X is normally distributed with a mean of 70 and a standard deviation of 10. What is the probability that X is between 72 and 84?


The time taken to assemble a car in a certain plant is a random variable having a normal distribution of 20 hours and a standard deviation of 2 hours. What is the probability that a car can be assembled at this plant in a period of time. Less than 19.5 hours?


The annual salaries of employees in a large company are approximately normally distributed with a mean of $50,000 and a standard deviation of $20,000. What percent of people earn less than $40,000?


X is a normally distributed variable with mean µ = 30 and standard deviation σ = 4. Find P(X < 40)


X is a normally distributed variable with mean µ = 30 and standard deviation σ = 4. Find P(30 < X < 35)


Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×