प्रश्न

In Bhagwati Mills Ltd. Thane standard labour cost of producing 500 metres of cloth has been specified as follows :
• Men Workers : 20 Hours @ Rs. 15 per hour
• Women Workers : 30 Hours @ Rs. 10 per hour
The actual cost data for producing 500 metres of cloth is as follows :
• Men Workers : 30 Hours @ Rs. 17 per hour
• Women Workers : 30 Hours@ Rs. 10 per hour
You ate required to calculate :
(i) Labour Cost Variance,
(ii) Labour Rate Variance,
(iii) Labour Efficiency Variance,
(iv) Labour Mix Variance.

Advertisements

उत्तर

Category of Workers Standard Actual Std. Proportion of Actual Input (Hrs.)
Quantity Rate(Rs.) Total(Rs.) Quantity Rate(Rs.) Total(Rs.)
Men Workers 20 15 300 30 17 510 24
Women Workers 30 10 300 30 10 300 36
  50   600 60   810 60

(i) Labour Cost Variance (LCV) = (Std. Hrs. x SR) - (Actual Hrs x AR)
Men Workers = (20 x 15) - (30 x 17) = Rs. 210 (A)
Women Workers = (30 x 10) - (30 x 10) = Rs. Nil
Rs. 210 (A)

(ii) Labciur Rate Variance (LRV) = (SR - AR) x Actual Hrs.
Men Workers = (15 - 17) x 30 = Rs. 60 (A)
Women Workers = (10 - 10) x 30 = Rs. Nil
Rs. 60 (A)

(iii) Labour Efficiency Variance (LEV) = (Std. Hrs. - Actual Hrs.) x SR.
Men Workers - (20 - 30) x 15 = Rs. 150(A)
Women Workers - (30 - 30) x 10 = Rs. Nil
Rs. 150. (A)

(iv) Labour Mix Variance (LMV) = SR x Difference in Mix
Men workers = (24 - 30) x 15 = Rs. 90 (A)
Unskilled = (36 - 30) x 10 = Rs. 60 (F)
Rs. 30 (A)