In Bhagwati Mills Ltd. Thane standard labour cost of producing 500 metres of cloth has been specified as follows :
• Men Workers : 20 Hours @ Rs. 15 per hour
• Women Workers : 30 Hours @ Rs. 10 per hour
The actual cost data for producing 500 metres of cloth is as follows :
• Men Workers : 30 Hours @ Rs. 17 per hour
• Women Workers : 30 Hours@ Rs. 10 per hour
You ate required to calculate :
(i) Labour Cost Variance,
(ii) Labour Rate Variance,
(iii) Labour Efficiency Variance,
(iv) Labour Mix Variance.
Advertisements
उत्तर
| Category of Workers | Standard | Actual | Std. Proportion of Actual Input (Hrs.) | ||||
| Quantity | Rate(Rs.) | Total(Rs.) | Quantity | Rate(Rs.) | Total(Rs.) | ||
| Men Workers | 20 | 15 | 300 | 30 | 17 | 510 | 24 |
| Women Workers | 30 | 10 | 300 | 30 | 10 | 300 | 36 |
| 50 | 600 | 60 | 810 | 60 | |||
(i) Labour Cost Variance (LCV) = (Std. Hrs. x SR) - (Actual Hrs x AR)
Men Workers = (20 x 15) - (30 x 17) = Rs. 210 (A)
Women Workers = (30 x 10) - (30 x 10) = Rs. Nil
Rs. 210 (A)
(ii) Labciur Rate Variance (LRV) = (SR - AR) x Actual Hrs.
Men Workers = (15 - 17) x 30 = Rs. 60 (A)
Women Workers = (10 - 10) x 30 = Rs. Nil
Rs. 60 (A)
(iii) Labour Efficiency Variance (LEV) = (Std. Hrs. - Actual Hrs.) x SR.
Men Workers - (20 - 30) x 15 = Rs. 150(A)
Women Workers - (30 - 30) x 10 = Rs. Nil
Rs. 150. (A)
(iv) Labour Mix Variance (LMV) = SR x Difference in Mix
Men workers = (24 - 30) x 15 = Rs. 90 (A)
Unskilled = (36 - 30) x 10 = Rs. 60 (F)
Rs. 30 (A)