A machine raises a load of 750 N through a height of 16 m in 5s. calculate:
(i) work done by machine,
(ii) power at which the machine works.
Advertisements
उत्तर
Given, load m = 750 N, displacement h = 16 m, time = 5 s, g = 10 N kg -1
now work done = mgh = 750 x 16 = 12000J
or power = `"work done"/"time taken" = 12000/5` = 2400 watt
APPEARS IN
संबंधित प्रश्न
It takes 20 s for a person A of mass 50 kg to climb up the stairs, while another person B does the same in 15 s. Compare the work done.
.A man raises a box of mass 50kg to a height of 2m in 20s, while another man raises the same box to the same height in 50s. Compare:
(i) the work done, and
(ii) the power developed by them.
Find the kinetic energy of a body of mass 1 kg moving with a uniform velocity of 10 m s-1.
Is it possible that a force is acting on a body but still the work done is zero? Explain giving one example.
If an electric bulb of 100 watt is lighted for 2 hours, how much electric energy would be consumed?
State larger units of power.