A and B can do a piece of work in 18 days; B and C in 24 days and A and C in 36 days. In what time can they do it, all working together?
Advertisements
उत्तर
\[\text{ Time taken by } \left( A + B \right) \text{ to do the work = 18 days } \]
\[\text{ Time taken by } \left( B + C \right) \text{ to do the work = 24 days } \]
\[\text{ Time taken by } \left( A + C \right) \text{ to do the work = 36 days } \]
\[\text{ Now } , \]
\[\text{ Work done by } \left( A + B \right) = \frac{1}{18}\]
\[ \text{ Work done by } \left( B + C \right) = \frac{1}{24}\]
\[ \text{ Work done by } \left( A + C \right) = \frac{1}{36}\]
\[ \therefore \text{ Work done together } = \left( A + B \right) + \left( B + C \right) + \left( A + C \right)\]
\[ = \frac{1}{18} + \frac{1}{24} + \frac{1}{36}\]
\[ = \frac{4 + 3 + 2}{72} = \frac{9}{72}\]
\[ = \frac{1}{8}\]
\[ \therefore \text{ Work done together } = 2\left( A + B + C \right) = \frac{1}{8}\]
\[ \therefore \text{ Work done by } \left( A + B + C \right) = \frac{1}{16}\]
\[ \text{ Thus, together they can finish the work in 16 days } .\]
APPEARS IN
संबंधित प्रश्न
Complite the following table given that x varies directly as y .
| x | 4 | 9 | ... | ... | 3 | ... |
| y | 16 | ... | 48 | 36 | ... | 4 |
The second class railway fare for 240 km of Journey is Rs 15.00. What would be the fare for a journey of 139.2 km?
The amount of extension in an elastic spring varies directly with the weight hung on it. If a weight of 250 gm produces an extension of 3.5 cm, find the extension produced by the weight of 700 gm.
8 men can do a piece of work in 9 days. In how many days will 6 men do it?
If the cost of 8 apples is ₹ 56 then the cost of 12 apples is _______
Both x and y are in direct proportion, then `1/x` and `1/y` are ______.
Write whether the following statement vary directly, vary inversely with each other, or neither of the two.
The number of people working and the quantity of work.
It is given that l varies directly as m. Find m when l is 8.
If 25 metres of cloth costs Rs 337.50, then what will be the cost of 40 metres of the same type of cloth?
If 25 metres of cloth costs Rs 337.50, then what will be the length of the cloth bought for Rs 810?