10 farmers can plough a field in 21 days. Find the number of days reduced if 14 farmers ploughed the same field?
Advertisements
उत्तर
Let the required number of days if 14 farmers ploughed = x
| Number of days | 21 | x |
| Number of farmers | 10 | 14 |
As number of farmers increases, number of days decreases.
∴ They are in inverse proportion
x1y1 = x2y2
21 × 10 = x × 14
x = `(21 xx 10)/14`
x = 15
Initially the farmers worked for 21 days.
Now they worked for 15 days.
∴ The number of days reduced = 21 – 15 = 6 days
APPEARS IN
संबंधित प्रश्न
A factory required 42 machines to produce a given number of articles in 63 days. How many machines would be required to produce the same number of articles in 54 days?
A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
A person has money to buy 25 cycles worth Rs 500 each. How many cycles he will be able to buy if each cycle is costing Rs 125 more?
If x and y vary inversely as other and x = 5 when y = 15, find x when y = 12 .
Mohanrao took 10 days to finish a book, reading 40 pages every day. How many pages must be read in a day to finish it in 8 days?
6 pumps are required to fill a water sump in 1 hr 30 minutes. What will be the time taken to fill the sump if one pump is switched off?
It takes 60 days for 10 machines to dig a hole. Assuming that all machines work at the same speed, how long will it take 30 machines to dig the same hole?
Meena had enough money to send 8 parcels each weighing 500 grams through a courier service. What would be the weight of each parcel, if she has to send 40 parcels for the same money?
Both x and y are said to vary ______ with each other if for some positive number k, xy = k.
If x varies inversely as y and x = 20 when y = 600, find y when x = 400.