Tamil Nadu Board of Secondary Education HSC Commerce इयत्ता ११ Question Bank Solutions for Business Mathematics and Statistics - Operations Research
Advertisements
Advertisements
Question bank solutions with answers for Business Mathematics and Statistics in Tamil Nadu Board of Secondary Education HSC Commerce इयत्ता ११.
Draw the network diagram for the following activities.
| Activity code | A | B | C | D | E | F | G |
| Predecessor activity | - | - | A | A | B | C | D, E |
पाठ: [10] Operations Research
Concept: undefined >> undefined
A Project has the following time schedule
| Activity | 1 - 2 | 2 - 3 | 2 - 4 | 3 - 5 | 4 - 6 | 5 - 6 |
| Duration (in days) |
6 | 8 | 4 | 9 | 2 | 7 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
पाठ: [10] Operations Research
Concept: undefined >> undefined
The following table gives the characteristics of the project
| Activity | 1 - 2 | 1 - 3 | 2 - 3 | 3 - 4 | 3 - 5 | 4 - 6 | 5 - 6 | 6 - 7 |
| Duration (in days) |
5 | 10 | 3 | 4 | 6 | 6 | 5 | 5 |
Draw the network for the project, calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and find the critical path. Compute the project duration.
पाठ: [10] Operations Research
Concept: undefined >> undefined
