Advertisements
Advertisements
Evaluate the following:
`lim_(x->∞) (sum "n")/"n"^2`
Concept: undefined >> undefined
Evaluate the following:
`lim_(x->0) (sqrt(1+x) - sqrt(1-x))/x`
Concept: undefined >> undefined
Advertisements
Evaluate the following:
`lim_(x->a) (x^(5/8) - a^(5/8))/(x^(2/3) - a^(2/3))`
Concept: undefined >> undefined
Evaluate the following:
`lim_(x->0) (sin^2 3x)/x^2`
Concept: undefined >> undefined
If `lim_(x->a) (x^9 + "a"^9)/(x + "a") = lim_(x->3)` (x + 6), find the value of a.
Concept: undefined >> undefined
If `lim_(x->2) (x^n - 2^n)/(x-2) = 448`, then find the least positive integer n.
Concept: undefined >> undefined
If f(x) = `(x^7 - 128)/(x^5 - 32)`, then find `lim_(x-> 2)` f(x)
Concept: undefined >> undefined
Let f(x) = `("a"x + "b")/("x + 1")`, if `lim_(x->0) f(x) = 2` and `lim_(x->∞) f(x) = 1`, then show that f(-2) = 0
Concept: undefined >> undefined
Examine the following function for continuity at the indicated point.
f(x) = `{((x^2 - 4)/(x-2) "," if x ≠ 2),(0 "," if x = 2):}` at x = 2
Concept: undefined >> undefined
Examine the following function for continuity at the indicated point.
f(x) = `{((x^2 - 9)/(x-3) "," if x ≠ 3),(6 "," if x = 3):}` at x = 3
Concept: undefined >> undefined
Show that f(x) = |x| is continuous at x = 0.
Concept: undefined >> undefined
Find the derivative of the following function from the first principle.
x2
Concept: undefined >> undefined
Draw the network for the project whose activities with their relationships are given below:
Activities A, D, E can start simultaneously; B, C > A; G, F > D, C; H > E, F.
Concept: undefined >> undefined
Find the derivative of the following function from the first principle.
log(x + 1)
Concept: undefined >> undefined
Draw the event oriented network for the following data:
| Events | 1 | 2 | 3 | 4 | 5 | 6 | 7 |
| Immediate Predecessors | - | 1 | 1 | 2, 3 | 3 | 4, 5 | 5, 6 |
Concept: undefined >> undefined
Construct the network for the projects consisting of various activities and their precedence relationships are as given below:
A, B, C can start simultaneously A < F, E; B < D, C; E, D < G
Concept: undefined >> undefined
Construct the network for each the projects consisting of various activities and their precedence relationships are as given below:
| Activity | A | B | C | D | E | F | G | H | I | J | K |
| Immediate Predecessors | - | - | - | A | B | B | C | D | E | H, I | F, G |
Concept: undefined >> undefined
Construct the network for the project whose activities are given below.
| Activity | 0 - 1 | 1 - 2 | 1 - 3 | 2 - 4 | 2 - 5 | 3 - 4 | 3 - 6 | 4 - 7 | 5 - 7 | 6 - 7 |
| Duration (in week) | 3 | 8 | 12 | 6 | 3 | 3 | 8 | 5 | 3 | 8 |
Calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity. Determine the critical path and the project completion time.
Concept: undefined >> undefined
Find the derivative of the following function from the first principle.
ex
Concept: undefined >> undefined
A project schedule has the following characteristics
| Activity | 1 - 2 | 1 - 3 | 2 - 4 | 3 - 4 | 3 - 5 | 4 - 9 | 5 - 6 | 5 - 7 | 6 - 8 | 7 - 8 | 8 - 10 | 9 - 10 |
| Time | 4 | 1 | 1 | 1 | 6 | 5 | 4 | 8 | 1 | 2 | 5 | 7 |
Construct the network and calculate the earliest start time, earliest finish time, latest start time and latest finish time of each activity and determine the Critical path of the project and duration to complete the project.
Concept: undefined >> undefined