Advertisements
Advertisements
प्रश्न
What was the outcome of Phase I of the Ganga Action Plan in terms of scheme completion?
विकल्प
261 schemes planned; 200 completed by 30-09-1999
261 schemes planned; 261 completed by 30-09-1999
300 schemes planned; 261 completed by 30-09-1999
261 schemes planned; 256 completed by 30-09-1999
MCQ
Advertisements
उत्तर
In Phase I of the Ganga Action Plan, 261 schemes were planned and 256 were completed by September 30, 1999. This represented a completion rate of approximately 98%, indicating substantial progress in implementing pollution control infrastructure. The progress was officially rated as satisfactory, with the approved budget of ₹462.04 crore nearly fully spent at ₹452 crore.
shaalaa.com
क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
