प्रश्न
Vaishali undertook a contract for the construction of house on 1.1.2017. The contract price was Rs. 22,50,000 The following details are available for 2017 :
| Particulars | (Rs.) |
| Materials purchased and issued | 3,60,000 |
| Materials issued from stores | 45,000 |
| Labour | 1,35,000 |
| Plant installed at site | 1,80,000 |
| Direct expenses | 90,000 |
| Establishment Charges | 22,500 |
| Materials returned to stores | 22,500 |
| Materials on hand at the end of the year | 9,000 |
| Plant in hand at the end of the year | 1,35,000 |
| Wages outstanding | 27,000 |
| Direct expenses outstanding | 36,000 |
| Work uncertified | 95,400 |
| Cash received (80% of work certified) | 9,00,000 |
Prepare the Contract Alc and show the relevant items in Balance Sheet.
Advertisements
उत्तर
Books of Vaishali
| Dr. | Contract A/c (For the Year 2017) | Cr. |
| Particulars | (Rs.) | Particulars | (Rs.) |
| To Material Purchased and Issued | 3,60,000 | By Materials returned to Stores | 22,500 |
| To Materials Issued from Stores | 45,000 | By Material on Hand | 9,000 |
| To Labour | 1,35,000 | By Plant in Hand | 1,35,000 |
| To Establishment Charges | 22,500 | By Work in Progress: | |
| To Wages (Outstanding) | 27,000 | Work Certified 11,25,000 | |
| To Direct Expenses (Outstanding) | 36,000 | Work Uncertified 95,400 | 12,20,400 |
| To Direct Expenses | 90,000 | ||
| To Plant Installed at Site | 1,80,000 | ||
| To Notional Profit c/d | 4,91,400 | ||
| 13,86,900 | 13,86,900 | ||
| To Profit and Loss Alc* | 2,62,080 | ||
| To Stock Reserve | 2,29,320 | By Notional Profit b/d | 4,91,400 |
| 4,91,400 | 4,91,400 |
Working Note:
(1) * Profit and Loss Alc : Contract Price = Rs. 22,50,000
Amount of work certified= Rs. 11,25,000
That means amount of work certified is `1/2` ( 50%) of contract price.
∴The following formula should be used =`2/3 xx "Notional Profit "xx "Cash Received"/"Work certified"`
∴ `2/3xx Rs. 4,91,400 xx (Rs.9,00,000)/(Rs.11,25,000)` = Rs. 2,62,080 (Profit and Loss Alc)
∴ Rs. 2,29,320 (Reserve)(Rs. 4,91,400 - Rs. 2,62,080)
Balance Sheet (Extracts Only)
| Liabilities | (Rs.) | Assets | (Rs.) | (Rs.) |
| Profit and Loss Alc | 2,62,080 | Work-in-Progress : | ||
| Outstanding Wages | 27,000 | Work Certified | 11,25,000 | |
| Outstanding Direct Expenses | 36,000 | (+)Work Uncertified | (+) 95,400 | |
| 12,20,400 | ||||
| (-)Reserve | 2,29,320 | |||
| (-)Cash received | 9,00,000 | 91,080 | ||
| Plant on Site at year End | 1,35,000 | |||
| Materials on Site at Year End | 9,000 |