Solve the following problem of sequencing for minimizing the total elapsed time and idle time for both the machines.

Advertisements
Advertisements

प्रश्न

Solve the following problem of sequencing for minimizing the total elapsed time and idle time for both the machines.

Job P Q R S T U
M1 1 4 6 3 5 2
M2 3 6 8 8 1 5

The optimal sequence of the jobs as follows:

           

Total elasped time is obtained as follows:

Job
sequence
Machine A Machine B Idle time for
Machine B
Time
In
Time
Out
Time
In
Time
Out
P `square` 1 1 `square` `square`
U `square` 3 4 `square` `square`
S `square` 6 9 `square` `square`
Q `square` 10 17 `square` `square`
R `square` 16 23 `square` `square`
T `square` 21 31 `square` `square`

Total elapsed time T = `square` minutes

Idle time for Machine A = T – `square` = `square` minutes

Idle time for Machine B = `square`

सारिणी
योग
Advertisements

उत्तर

Job P Q R S T U
M1 1 4 6 3 5 2
M2 3 6 8 8 1 5

The optimal sequence of the jobs as follows:

P U S Q R T

Total elapsed time is obtained as follows:

Job
sequence
Machine A Machine B Idle time for
Machine B
Time
In
Time
Out
Time
In
Time
Out
P 0 1 1 4 1
U 1 3 4 9 0
S 3 6 9 17 0
Q 6 10 17 23 0
R 10 16 23 31 0
T 16 21 31 32 0

Total elapsed time T = 32 minutes

Idle time for Machine A = T – 21 = 11 minutes

Idle time for Machine B = 1

shaalaa.com
Sequencing Problem
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
अध्याय 2.7: Assignment Problem and Sequencing - Q.5
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×