प्रश्न

From the following information calculate:
(i) Labour Cost Variance,
(ii) Labour Rate Variance,
(iii) Labour Efficiency Variance.

Gross direct wages Rs. 3,000
Standard hours for production 1,600 Hrs.
Standard rate per hour Rs. 1.50
Actual hours for Production 1,500 Hrs.
Advertisements

उत्तर

Calculation of Standard Gross Wages :
Standard Gross Wages = Standard Hours. x Standard Rate per Hour
= 1,600 Hours x Rs. 1.50
∴ Standard Gross Wages = Rs. 2,400
Calculation of Actual Rate of Wages :
`"Actual Rate of Wages"="Actual wages"/"Actual hours"`

`=("Rs."3,000)/(1,500 "hours")`

∴ Actual Rate of Wages = Rs. 2

Standard Actual
Hours Rate(Rs.) Total(Rs.) Hours Rate(Rs.) Total(Rs.)
1,600 1.50 2,400 1,500 2 3,000
1,600   2,400 1,500   3,000

(i) Labour Cost Variance (LCV) - (S Hrs. x SR) - (Actual Hrs. x AR)
∴ LCV = (1,600 x 1.50) - ( 1,500 x 2)
∴ LCV = Rs. 2,400 (-) 3,000
∴ LCV = Rs. 600 (A)

(ii) Labour Rate Variance (LRV) = (SR - AR) x Actual Hrs.
∴ LRV = (1.50 - 2.00) x 1,500
∴ LRV = Rs. 750 (A)

(iii) Labour Efficiency Variance (LEV) = (Std. Hrs. -Actual Hrs.) x SR
∴ LEV = (1,600 - 1,500) x Rs. 1.50
∴ LEV = Rs. 150 (F)