Choose the correct statement about the controlling function of management.
विकल्प
No corrective action is required when the deviation goes beyond the acceptable range in important areas.
Deviations should be analysed for their causes.
Measurement of actual performance should be done only after the task is complete.
Managers must keep a check on each and every activity, otherwise the entire organisation may suffer.
Advertisements
उत्तर
Deviations should be analysed for their causes.
Explanation:
In the controlling function of management, managers compare actual performance with planned performance. If there are deviations, they must be analysed to find their causes so that corrective actions can be taken. This helps improve future performance and ensures goals are achieved efficiently. Hence, the correct statement is “Deviations should be analysed for their causes.”