Advertisements
Advertisements
प्रश्न
A takes 6 days less than the time taken by B to finish a piece of work. If both A and B work together they can finish in 4 days. Find the time taken by B to finish the work.
Advertisements
उत्तर
Let B take 'c' days to finish the work. Hence, A will take 'c- 6' days.
⇒ Work done by B in One day = `1/"c"` , whereas work done by A in one day = `1/("c" - 6)`
⇒ Work done by A and B combined in one day = `1/"c" + 1/("c" + 6) = ("c" - 6 + "c")/c`
Together they can complete the work in 4 days, hence:
`("c"^2 - 6"c")/(2"c" - 6) = 4`
⇒ c2 - 6c = 8c - 24
⇒ c2 -14c + 24 = 0
⇒ c2 -12c - 2c + 24 = 0
⇒ c (c -12) - 2{c - 12) = 0
⇒ (c -12) {c - 2) = 0.
It can't be 2 as they together complete in 4 days and hence has to be more than that.
Hence no. of days taken by B to finish the work = 12
