We Have Seven Jobs Each of Which Has to Go Through Two Machines M1 and M2 in the Order M1 - M2 . Processing Times (In Hours) Are Given as : Jobs A B C D E F G Machine M1 3 12 15 6 10 11 9 Ma - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

We have seven jobs each of which has to go through two machines M1 and M2 in the order  M1 - M2 . Processing times (in hours) are given as :

Jobs  A B C D E F G
Machine M 3 12 15 6 10 11 9
Machine M2 8 10 10 6 12 1 3

Determine a sequence of these jobs that Will minimize the total elapsed time 'T', and idle time for each machine .

बेरीज
Advertisements

उत्तर

The order is M1 M2. hence required sequence is 

A D E C B G F

Or

A E B C D G F

 

Job seq.      Machine M1      Machine M2
Time in Time out Time in  Time out
A 0 3 3 11
D 3 9 11 17
E 9 19 19 31
C 19 34 34 44
B 34 46 46 56
G 46 55 56 59
F 55 66 66 67

Total elapsed time T = 67 hrs. 
Idle time for Machine M1 = 1 hr. 
Idle time for Machine M2 = 17 hrs. 

shaalaa.com
Sequencing in Management Mathematics