Time taken by a construction company to construct a flyover is a normal variate with mean 400 labour days and a standard deviation of 100 labour days. If the company promises to construct the flyover in 450 days or less and agree to pay a penalty of ₹ 10,000 for each labour day spent in excess of 450. What is the probability that the company takes at most 500 days to complete the flyover?
Advertisements
उत्तर
Let x be a normal variate with mean 400 labour days and standard deviation of 100 labour days
m = 400 and σ = 100
The construction work should be completed within 450 days.
The standard normal variate
`(x - mu)/6 = (x - 400)/100`
Personality for 1 labour day = ₹ 10,000
P(at most 500 days) = P(X ≤ 500 )
When x = 500
z = `(500 - 400)/100 = 100/100` = 1
P(X ≤ 500) = P(Z ≤ 1)
=P(`∞` < z < 0) – r – P(0 < z < 1)
= 0.5 + 0.3415
= 0.8413
APPEARS IN
संबंधित प्रश्न
Derive the mean and variance of binomial distribution
If 5% of the items produced turn out to be defective, then find out the probability that out of 20 items selected at random there are exactly three defectives
In a particular university 40% of the students are having newspaper reading habit. Nine university students are selected to find their views on reading habit. Find the probability that all those selected have newspaper reading habit
If the probability of success is 0.09, how many trials are needed to have a probability of atleast one success as 1/3 or more?
A pair of dice is thrown 4 times. If getting a doublet is considered a success, find the probability of 2 successes
An experiment succeeds twice as often as it fails, what is the probability that in next five trials there will be three successes
Write the conditions for which the poisson distribution is a limiting case of binomial distribution
The mortality rate for a certain disease is 7 in 1000. What is the probability for just 2 deaths on account of this disease in a group of 400? [Given e–2.8 = 0.06]
Choose the correct alternative:
If P(Z > z) = 0.5832 what is the value of z (z has a standard normal distribution)?
X is a normally distributed variable with mean µ = 30 and standard deviation σ = 4. Find P(X > 21)