The Given Problem is of N Jobs and Three Machines. We Change the Problem in of N Jobs and Two Machines. - Mathematics and Statistics

Advertisements
Advertisements

प्रश्न

There are found jobs to be completed. Each job must go through machines M1 , M2 , M3 in the order M1 - M2 - M3.  Processing time in hours is given below. Determine the optimal sequesnce and idle time for machine M1 .

Jobs A B C D
M1 5 8 7 3
M2 6 7 2 5
M3 7 8 10 9
बेरीज
Advertisements

उत्तर

Given ,

Jobs A B C D
M1 5 8 7 3
M2 6 7 2 5
M3 7 8 10 9

Here Min. (M1) = 3 , Min. (M3) = 7 . Max.(M2) = 7  Min. (M3) ≥ Max.(M2)

∴ The problem can be converted into

2 machine , 4 jobs problem.

Let G = M1 + M2 , H = M2 + M3

  A B C D
G 11 15 9 8
H 13 15 12 14

Here Min . (Gi1 , Hi2 ) = 8

corresponding to machine G , job D.

∴ job D is processed first.

D      

The problem now reduced to 2 machines , 3 job problem.

Now Min. (Gi1 , Hi2 ) = 9 ,  corresponding to machine G , job C

∴ job C is processed second.

D C    

Here Min . (Gi1 , Hi2 ) = 11 , corresponding to machine G , job A.

∴ job A is processed third.

D C A  

The optimal sequence of jobs is obtained as follows : 

D C A B

 

Job `"M"_1` `"M"_2` `"M"_3`
  Time in Time out Time in  Time out Time in Time out
D 0 3 3 8 8 17
C 3 10 10 12 17 27
A 10 15 15 21 27 34
B 15 23 23 30 34 42

The minimum elapsed time = 42 hrs.
Ideal time for `M_1` = 42 – 23 = 19 hrs.