If jobs I, II, III have processing times as 8, 6, 5 on machine M1 and 8, 3, 4 on machine M2 in the order M1-M2, then the optimal sequence is ______.
पर्याय
I, II, III
I, III, II
II, I, III
III, II, I
MCQ
रिकाम्या जागा भरा
Advertisements
उत्तर
If jobs I, II, III have processing times as 8, 6, 5 on machine M1 and 8, 3, 4 on machine M2 in the order M1-M2, then the optimal sequence is I, III, II.