If jobs I, II, III have processing times as 8, 6, 5 on machine M1 and 8, 3, 4 on machine M2 in the order M1-M2, then the optimal sequence is ______.

पर्याय

  • I, II, III

  • I, III, II

  • II, I, III

  • III, II, I

MCQ
रिकाम्या जागा भरा
Advertisements

उत्तर

If jobs I, II, III have processing times as 8, 6, 5 on machine M1 and 8, 3, 4 on machine M2 in the order M1-M2, then the optimal sequence is I, III, II.