Complete the following cost schedule :
| Quantity (in Units) | 0 | 1 | 2 | 3 | 4 |
| Total cost (in ₹) | 200 | ....... | ....... | ....... | ....... |
| Total variable cost (in ₹) | 0 | ....... | 180 | ....... | ....... |
| Average variable cost (in ₹) | ....... | 100 | ....... | 80 | ....... |
रिकाम्या जागा भरा
Advertisements
उत्तर
| Quantity | Total Cost | Total Variable Cost | Average Variable Cost | Total Fixed Cost |
| 0 | 200 | 0 | - | 200 |
| 1 | 300 | 100 | 100 | 200 |
| 2 | 380 | 180 | 90 | 200 |
| 3 | 440 | 240 | 80 | 200 |
| 4 | 490 | 290 | 72.5 | 200 |