मराठी

An important project at AMB Consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run.

Advertisements
Advertisements

प्रश्न

An important project at AMB Consultants is running behind schedule by a month. This has upset their clients and might affect the reputation of the company in the long run. No managerial action like assigning more workers, equipment or giving overtime has been able to solve the problem. What managerial action may now be taken by the company to avoid such a situation from arising in future?

पर्याय

  • Revise the schedule

  • Assigning additional workers and equipment to the project

  • Get permission for further overtime work

  • Both (2) and (3)

MCQ
Advertisements

उत्तर

Revise the schedule

shaalaa.com
Techniques of Managerial Control
  या प्रश्नात किंवा उत्तरात काही त्रुटी आहे का?
Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×