प्रश्न
There are 5 jobs each of which is to be processed through three machines A, B and C in the order ABC. Processing times in hours are as shown in the following table :
| Job | 1 | 2 | 3 | 4 | 5 |
| A | 3 | 8 | 7 | 5 | 4 |
| B | 4 | 5 | 1 | 2 | 3 |
| C | 7 | 9 | 5 | 6 | 10 |
Determine the optimum sequence for the five jobs and the minimum elapsed time.
योग
Advertisements
उत्तर
Min MA = 3, Max MB = 5 and Min Mc = 5
∵ Min Mc ≥ Max MB
∴ Let G = A + B ; H = B + C
The problem is
| Jobs | 1 | 2 | 3 | 4 | 5 |
| G | 7 | 13 | 8 | 7 | 7 |
| H | 11 | 14 | 6 | 8 | 13 |
the optimal sequence is
4 1 5 2 3
| Job | Machine A | Machine B | Machine C | |||
| In | Out | In | Out | In | Out | |
| 4 | 0 | 5 | 5 | 7 | 7 | 13 |
| 1 | 5 | 8 | 8 | 12 | 13 | 20 |
| 5 | 8 | 12 | 12 | 15 | 20 | 30 |
| 2 | 12 | 20 | 20 | 25 | 30 | 39 |
| 3 | 20 | 27 | 27 | 28 | 39 | 44 |
∴ Minimum elapsed time = 44 hrs