There are 5 jobs each of which is to be processed through three machines A, B and C in the order ABC. Processing times in hours are as shown in the following table : 

Job 1 2 3 4 5
A 3 8 7 5 4
B 4 5 1 2 3
C 7 9 5 6 10

Determine the optimum sequence for the five jobs and the minimum elapsed time. 

योग
Advertisements

उत्तर

Min MA = 3,  Max MB = 5  and Min Mc = 5 

∵ Min M ≥ Max MB 

∴ Let G = A + B ; H = B + C

The problem is

Jobs 1 2 3 4 5
G 7 13 8 7 7
H 11 14 6 8 13

the optimal sequence is 

4   1    5     2   3 

Job Machine A Machine B Machine C
In Out In Out In Out
4 0 5 5 7 7 13
1 5 8 8 12 13 20
5 8 12 12 15 20 30
2 12 20 20 25 30 39
3 20 27 27 28 39 44

∴ Minimum elapsed time = 44 hrs

shaalaa.com
Sequencing in Management Mathematics
  क्या इस प्रश्न या उत्तर में कोई त्रुटि है?
2015-2016 (July)

APPEARS IN

Share
Notifications

Englishहिंदीमराठी


      Forgot password?
Use app×