The following are the details for a job which is expected to be completed within 50 weeks.

Grade of Workers Standard Actual
No. of Workers Wage Rate Per Worker (Weekly) (Rs.) No. of Workers Wage Rate Per Worker (Weekly) (Rs.)
Skilled 80 75 70 80
Semi-skilled 40 50 40 60
Unskilled 50 35 50 20

55 weeks were taken to complete the job.
Calculate the various Labour Variances.

Advertisements

उत्तर

Grade of Workers Standard Actual Standard Proportion of Actual Weeks
Weeks Rate (Rs.) Total (Rs.) Weeks Rate (Rs.) Total (Rs.)
Skilled 80 x 50 = 4,000 75 3,00,000 70 x 55 = 3,850 80 3,08,000 4,141
Semi-skilled 40 x 50 = 2,000 50 1,00,000 40 x 55 = 2,200 60 1,32,000 2,071
Unskilled 50 x 50 = 2,500 35 87,500 50 x 55 = 2,750 20 55,000 2,588
  8,500   4,87,500 8,800   4,95,000 8,800

(a) Labour Rate Variance = (SR - AR) x Actual Time
Skilled : (75 - 80) x 3,850 weeks = Rs. 19,250 (A)
Semi-skilled : (50- 60) x 2,200 weeks = Rs. 22,000 (A)
Unskilled : (35 - 20) x 2,750 weeks · = Rs. 41,250 (F)
NIL

(b) Labour Efficiency Variance = (Std. Time - Actual Time) x SR
Skilled :
(4,000 weeks - 3,850 weeks) x 75 = Rs. 11.250 (F)
Semi-skilled : (2,000 weeks - 2,200 weeks) x 50 = Rs. 10,000 (A)
Unskilled : (2,500 weeks - 2,750 weeks) x 35 = Rs. 8,750 (A)
Rs. 7,500 (A)

(c) Labour Cost Variance= SC - AC
Skilled
: Rs. 3,00,000 - Rs. 3,08,000 = Rs. 8,000 (A)
Semi-skilled
: Rs. 1,00,000 - Rs. 1,32,000 = Rs. 32,000 (A)
Unskilled
: Rs. 87,500 - Rs. 55,000 = Rs. 32,500 (F)
Rs. 7,500 (A)

(d) Labour Mix Variance = SR x Difference in Mix
Skilled
: 75 x (4,141 - 3,850) = Rs. 21,825 (F)
Semi-skilled
: 50 x (2,071 - 2,200) = Rs. 6,450 (A)
Unskilled
: 35 x (2,588 - 2, 750) = Rs. 5,670 (A)
Rs. 9,705 (F)

Answers:
(a) Labour Rate Variance = Rs. NIL.
(b) Labour Efficiency Variance = Rs. 7,500 (A).
(c) Labour Cost Variance = Rs. 7,500 (A).
(d) Labour Mix Variance = Rs. 9,705 (F).

Verification :
LRV + LEV - LCV
∴ Rs. (NIL) + Rs. 7,500 (A) = LCV
Rs. 7,500 (A)  = Rs. 7,500 (A)

Working Notes :
(1) Standard Proportion of Actual Weeks (8,800 weeks) are distributed among the three grades of workers in the ratio of 4,000 : 2,0QO : 2,500 i.e. (8 : 4 : 5) in the following way.

Skilled `=8,800xx8/17=4,141. `

Senii-skilled `=8,800xx4/17=2,071. `

Unskilled `=8,800xx5/17=2,588. `